Data centres

Platform steel, plant yards, containment support and mezzanines, on programmes where repeatability and delivery sequence matter more than tonnage.

  1. Repeatability is the whole strategy
  2. The steel waits on the MEP model
  3. Delivery sequence is the deliverable

Continuous line: Issued Dotted line: Not yet issued Dashed line: By others Leader line: Refers to

Sample line of balance by release lot, generated for this site. In steps, not days. Not a Seimora project.

Data centre steel is not structurally demanding and is programme-critical, which is an unusual combination. The frames, plant platforms, generator and chiller yards, containment and cable tray supports and mezzanines are all ordinary structures. What is not ordinary is that the building has a commissioning date the business has already sold against, and steel sits early enough in the sequence to move it.

Repeatability is the whole strategy

These campuses build the same hall several times. The value of getting the first one detailed properly — standard connections, a marking convention that survives a repeat, a bill of material that can be re-issued rather than rebuilt — compounds across every subsequent building. Work that treats building two as a fresh job throws that away.

The steel waits on the MEP model

Containment and equipment support cannot be finalised before the services are, and the services are rarely finished when the programme says the steel must be released. The practical answer is release by lot: the structure whose loads are known goes first, and the supports that depend on late data are isolated into their own release rather than holding the frame. That requires the model to be federated and the lot boundaries to be deliberate — see BIM & digital delivery.

Delivery sequence is the deliverable

On a site erecting continuously, a truck arriving with the right tonnage in the wrong order costs a day. Load plans are built from the erection sequence backwards.

Sample model. Not a Seimora project. Not a data centre project. Lit: the duct by others, for The steel waits on the MEP model. Dashed: work by others. Drag to rotate, pinch or use the buttons to zoom. Click a member.Loading the sample model.

Send the scope

A model, a drawing set or a written description. The specification and the required-on-site date tell us more than the size of the job does.